COOS BAY — A project administrators dreamed about 19 years ago is now 90% complete on the Southwestern Oregon Community College campus.

The college’s Umpqua Health & Science Technology Building is expected to be done in time for its January 2021 opening. A grand opening ceremony has been pushed from October to sometime in December. 

There have been a few delays along the way due to the COVID-19 pandemic, but overall, construction of the 36,000 square-foot project has been on schedule. The original $21.5-million budget has gone up to $24 million, as material costs have increased since the project began. Southwestern fundraised vigorously to qualify for an $8 million match from the state for construction of the building, with funds also provided from state bonds, federal grants and many generous private donations.

The pandemic has slowed things a little, said Leonard Phearson, project superintendent with Bogatay Construction of Klamath Falls,